PRTE

Scheduling Data for Project Item | #transactional | Component: Dates
Column Name Description
MANDT FK Client
POSNR FK WBS Element
Column Name Description
Column Name Description
📏 Unit for duration of basic WBS element dates (PEINH):
PDAUR Length (duration) of the basic dates in the WBS element
📏 Unit for duration of WBS element planned dates (EEINH):
EDAUR Forecasted length (duration) of the WBS element
📏 Unit for duration of actual WBS element dates (IEINH):
IDAUR Actual length (duration) of the WBS element
Column Name Description
PSTRT WBS element: Basic start date
ESTRT Forecast Start Date of WBS Element
ISTRT Actual start date for the WBS element
PENDE WBS element: Basic finish date
EENDE Forecast Finish Date of WBS Element
IENDE Actual finish date of the WBS element
PSTRM Earliest scheduled start date (Basic)
PETRM Latest scheduled finish date (basic)
ESTRM Scheduled start date (Forecast)
EETRM Latest scheduled finish date (Forecast)
VISTR Tentative actual start date for WBS element
VIEND Tentative actual finish date for WBS element
PSTRS Latest scheduled start date (basic)
PETRF Earliest scheduled finish date (basic)
ESTRS Latest scheduled start date (forecast)
EETRF Earliest scheduled finish date (forecast)
Column Name Description
FLGVG Indicator: There are activities for the WBS elements Show values
FLGEW Indicator: Expected dates from the activities Show values
FLGEM Indicator: Forecast dates set manually Show values
FLGVM Indicator: Basic dates set manually Show values
FLGIM Indicator: Actual dates set manually Show values
FLGVI Indicator: Actual dates from the activities Show values
Column Name Description Domain name
Master Data Relations Join Conditions
Client PRTE.MANDT == T000.MANDT
Current number of the appropriate project
  • PRTE.MANDT == PROJ.MANDT
  • PRTE.PSPHI == PROJ.PSPNR