- Application Platform (AP)
- Basis Components (BC)
- Business Mobile (MOB)
- Business Network Solutions (BNS)
- Controlling (CO)
- Cross-Application Components (CA)
- Cross-Application Components (CA)
- Customer Relationship Management (CRM)
- Enterprise Contract Management (CM)
- Enterprise Controlling (EC)
- Enterprise information management solutions (EIM)
- Environment, Health, and Safety / Product Compliance (EHS)
- Financial Accounting (FI)
- Financial Services (FS)
- Global Trade Services (SLL)
- Investment Management (IM)
- LOD Components (LOD)
- Legal Content Management (LCM)
- Logistics - General (LO)
- Logistics Execution (LE)
- Materials Management (MM)
- Occasional Platform User (OPU)
- Payroll (PY)
- Personnel Management (PA)
- Plant Maintenance (PM)
- Portfolio and Project Management (PPM)
- Product Lifecycle Management (PLM)
- Production Planning and Control (PP)
- Project System (PS)
- Claim Management (PS-CLM)
- Functions for U.S. Federal Government (PSM-FG)
- Fund Accounting (PSM-FA)
- Funds Management (PSM-FM)
- Grants Management (PSM-GM)
- Information System (PS-IS)
- Procurement for Public Sector (PSM-GPR)
- Project Billing (PS-BIL)
- Project Demand (PS-DMN)
- Revenues and Earnings (PS-REV)
- Simulation (PS-SIM)
- Structures (PS-ST)
- Virtual Data Model for Project System (PS-VDM)
- Public Sector Management (PSM)
- Purchasing SAP Cloud (PUR)
- Quality Management (QM)
- Real Estate Management (RE)
- SAP Business Warehouse (BW)
- SAP Supplier Lifecycle Management (SLC)
- Sales and Distribution (SD)
- Service (SV)
- Supply Chain Management (SCM)
- Sustainability management (SUS)
- Transportation Management (TM)
C_NetworkActivityBasicInfo
Network Activity Basic Information
| view: CNTWKACTYBSCINFO
| Extraction:
Not supported
| Component: Structures
Tables used:
AFKO, AFVC, AFVU, AFVV, JEST, PRTE, TGSB, TGSBT, T001, TKA02, TKA01, CSLA, CSLT, CSKA, CSKU, TFKB, TFKBT, T023, T023T, AUFK, T430, T430, VSAFKO_CN, VSAFVC_CN, VSAFVU_CN, VSAFVV_CN, VSAUFK_CN, T430, T430T, T001W, TCN07, TCN7T, CRTX, CEPC, CEPC, CEPCT, PROJ, PROJ, CNLDST_SHORTTX, CNLDST_SHORTTX, VSPROJ_CN, T024, T024E, T000, LFA1, TTXJ, TTXJT, PRPS, VSPRPS_CN, VSPRTE_CN, CRHD, CNLDST_OBJS
Column Name | Description | |
---|---|---|
ProjectNetwork FK | Order Number | |
NetworkActivity | Activity Number | |
SuperiorNtwkActivityExternalID | Activity element number (work/external/general costs) | |
Version | Version |
Column Name | Description | |
---|---|---|
💲 Currency Key (NetworkActivityCurrency): | ||
ExternalProcessingPrice | Price | |
NetworkActivityCost | Costs in the activity |
Column Name | Description | |
---|---|---|
📏 Normal Duration/Unit (StandardDurationUnit): | ||
StandardDuration | Duration of Activity | |
📏 Unit for Work (NtwkActivityWorkQuantityUnit): | ||
PlannedWorkQuantity | Work involved in the activity | |
ForecastedWorkQty | Forecasted work (actual + remaining) | |
ActualWorkQuantity | Actual work | |
RemainingWorkQuantity | Remaining Work | |
📏 Unit of measure for activity (NetworkActivityQuantityUnit): | ||
ActivityQuantity | Activity Total Quantity |
Column Name | Description | |
---|---|---|
SchedldBasicLatestStartDate | Latest scheduled start date (basic) | |
ScheduledBasicLatestEndDate | Latest scheduled finish date (basic) | |
SchedldBasicEarliestStartDate | Earliest scheduled start date (Basic) | |
SchedldBasicEarliestStartTime | Earliest scheduled start: Execution (time) | |
SchedldBasicEarliestEndDate | Earliest Finish Date | |
SchedldBasicEarliestEndTime | Earliest scheduled finish: Execution (time) | |
SchedldBasicLatestStartTime | Latest scheduled start: Execution (time) | |
SchedldBasicLatestEndTime | Latest scheduled finish: Execution (time) | |
SchedldFcstdEarliestStartDate | Scheduled start date (Forecast) | |
SchedldFcstdEarliestStartTime | Earliest scheduled start time (forecast) | |
LatestSchedldFcstdStartDate | Latest scheduled start date (forecast) | |
SchedldFcstdLatestStartTime | Latest scheduled start time (forecast) | |
SchedldFcstdEarliestEndDate | Earliest scheduled finish date (forecast) | |
SchedldFcstdEarliestEndTime | Earliest scheduled finish time (forecast) | |
LatestSchedldFcstdEndDate | Latest scheduled finish date (Forecast) | |
SchedldFcstdLatestEndTime | Latest scheduled finish time (forecast) | |
ActualStartDate | Actual start date for the WBS element | |
ActualExecutionStartTime | Actual Execution Start Time | |
ActualEndDate | Actual finish date of the WBS element | |
ActualExecutionEndTime | Actual Execution End Time |
Column Name | Description | |
---|---|---|
ActyBscStartDateConstraintType | Constraint on the basic start date for the activity | Show values |
ActyBscEndDateConstraintType | Constraint on the finish date of the activity | Show values |
IsMarkedForDeletion | Deletion Indicator | Show values |
Column Name | Description | Domain name | |
---|---|---|---|
NetworkActivityDescription | Operation short text | ||
ProjectNetworkInternalID | Routing number of operations in the order | AUFPL | |
Plant | Plant | WERKS | |
OperationControlProfileName | Operation Control Profile Name | TEXT40 | |
PlantName | Plant Name | TEXT30 | |
NetworkActivityPriority | Priority | PRIORITAET | |
WorkCenter | Work Center | ARBPL | |
WorkCenterText | Operation Control Profile Name | TEXT40 | |
CostElementName | Search Term For Matchcode Search Cost Element | CHAR20 |
Master Data Relations | Join Conditions |
---|---|
Cost Element
| |
Appointments: Calendar | C_NETWORKACTIVITYBASICINFO.FACTORYCALENDAR == TFACD.IDENT |
Control Key
| |
Currency Key
| |
Unit of measure for activity
| |
Unit for Work
| |
Order Number
| |
Normal Duration/Unit
| |
Account Number of Supplier
|